img

Operation and Maintenance of New Offshore Export Facilities

Mooring Hawser Handling

Mooring Hawser Handling and Securing Tankers During Berthing/Un-berthing

Mooring Hawser Handling

SPM Preparation for Loading Operations

Mooring Hawser Handling

CMMP Taker Pre-Arrival Check

Mooring Hawser Handling

Floating Hose Hookup

Mooring Hawser Handling

Operation of Berthing / Mooring Tugs

Mooring Hawser Handling

Floating Hose Handling

Section 3 Image

Project Scope

SPMs Operation and Maintenance:

Marine Operation: VLCC Tanker (>350,000 Ton) Tankers’ Berthing, Un-Berthing and Loading Operation,
Planned & Unplanned Maintenance of SPM 185, 2&3 Regular Class inspection and renewal

Plant Daily Production/Export Rate:

1.1 Million Barrel Per Day – ABOT

Over 2.2 Million Barrel Per Day – SPM Facilities

Project Resources:

  1. Over 100 Manpower
  2. Marine Spread(15 Vessels)
    1. 5 Mooring Tug
    2. 5 Berthing Tug
    3. Diving Support Vessel
    4. Accommodation Barge for Manpower
    5. Oil Spill response Eq.
    6. Diving Spread
    7. Fast Rescue and Crew Vessels
  3. Capital Spares, 2Yrs Spares of Plant
  4. Consumables for 2Yrs of Plant Operation

Design and Engineering for 120POB Offshore Accommodation Module

Design and Engineering Image Design and Engineering Image

Single Point Mooring

Technical Element
Main Components
Power Supply System
Solar Panel, Battery
Control System
PMS, Control system, Telemetry
Piping System
Product Swivel, Floating / Subsea hose
Hydraulic System
Hydraulic Swivel, HPU, Umbilical
Mooring System
Hawser, Anchor system, Chain stopper
Turret
Turret, Main Bearing
Structure
Buoy, Deck House, Boat landing
Single Point Mooring Illustration

Fabrication Sequence

Fabrication Sequence

Material Receipt

Material Receipt

Material Receipt

Material Inspection

Material Receipt

Fit up (1)

Material Receipt

Fit up Inspection

Material Receipt

Welding (1)

Material Receipt

Welding (2)

Material Receipt

NDE

Material Receipt

Welding Inspection

Material Receipt

Assembly

Material Receipt

Bearing Support Final machining

Material Receipt

Final Assembly Completion

Material Receipt

Painting Completion

Summary of Technology Development

1.4. SPM Structural Fabrication
Deck house, Buoy body & Turret Fabrication

Promotion Results

  • SPM fabrication execution plan preparation and overall production completion.
  • Preparation WPS&PQR for Structure Welding Reliability Verification and Performing inspection during presence of the inspector
  • Preparation WPS&PQR for Structure Welding Reliability Verification and Performing inspection during presence of the inspector
  • Preparation of inspection and test plan (ITP), material, fit-up, welding, NDE, paint and inspection test procedures
  • Complete Preparation of Assembly & Erection Plan and whole assembly

SPM Structural Fabrication

Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt
Material Receipt

Design and Supply Quick Release Hook System for Offshore Mooring Terminals